The Confusion between Necessity and Proportionality of State Aid [Case SA.35738: Public Funding of Port Infrastructure]

port

Introduction

Several postings in this blog have examined cases concerning funding of port, airport or sport infrastructure. These cases have all had interesting peculiarities. Some involved no state aid because public authorities acted as private investors, while in other cases the funding arrangements were designed in such a way so that the state aid to operators would not spill over to users of the infrastructure.

This posting examines yet another Commission decision on public funding of infrastructure. There are two notable issues in this case. First, while the funding of the operator does constitute state aid, the construction of certain parts of the port facilities falls outside the scope of Article 107(1) TFEU because they are linked to the official functions of the state. Second, the proportion of public funding is very high, yet financial calculations purport to show that the aid is proportional. I will explain that these calculations demonstrate only the necessity of the aid for the project as a whole but not the proportionality of the aid.

The project[1]

Greek authorities intend to grant EUR 11.2 million to an infrastructure project at the port of Katakolo in western Peloponnese. The usage and exploitation of the port has been assigned to the “Pyrgos Municipal Port Fund” (PMPF) which is a public law legal entity. The objective of the project is to improve and expand the existing port facilities (piers and buildings) and upgrade safety features. The project includes the construction of a new building for port traffic and passport control. The cost of this building is not included in the notification, because the Greek authorities claim that it is not related to the economic activities of the port.

The total notified investment cost (without the new building for port traffic and passport control) is EUR 12.3 million. The cost is covered by the following contributions: EUR 1.7 million by the Greek state, EUR 9.5 million by the ERDF (which corresponds to a rate of co-financing of 85% and brings the total amount of public money to EUR 11.2 million) and EUR 1.1 million by the beneficiary (i.e. the PMPF). The resulting aid intensity is 91.23%.

The public financing will take the form of direct grants to PMPF, which will be given gradually as the upgrading works progress. The works will be contracted out on the basis of a public, open and non-discriminatory tender procedure, in compliance with EU public procurement law.

According to financial and economic cost-benefit analysis carried out by the Greek authorities, over a reference period of 25 years, the project has a negative financial net present value (i.e. funding gap) of – EUR 10.2 million. The funding gap ratio, calculated as the ratio between the net present value of the project and the discounted total cost of the project, which is EUR 11.1, is 91.23%. This indicates that the investment project is not financially sustainable and would not be concluded without significant public support.

Existence of state aid

The Commission found that the sum of the public funding (i.e. both the money from the state and the money from the ERDF) satisfied all the criteria of Article 107(1). The contribution of the ERDF came under the control of the state and it was thus classified as state resource. The PMPF, the recipient, was an undertaking by virtue of the fact that it carried out an economic activity, given that the construction and exploitation of port infrastructure is an economic activity. The PMPF certainly obtained an economic advantage because the cost-benefit analysis showed that the project had a negative net present value and would not have been undertaken by private investor. For similar analysis, see, for example, Commission Decision N 385/2009 (Ventspils port), Commission Decision N 44/2010 (Krievu Sala port), Commission Decision SA.30742 (Klaipeda port) and Commission Decision SA.34940 (Augusta port).

The Commission accepted the view of the Greek authorities that the new building for port traffic and passport control would be linked to the exercise of public authority and would not be of an economic nature. Consequently, its public funding would not constitute state aid. Examples of public tasks (i.e. tasks that fall within the remit of the state) are security, safety, police services, or environmental protection functions, “insofar as they are not an intrinsic part of a project with a commercial end” and provided that the funding of such tasks is limited to what is necessary without any spillover to commercial activities.

With regard to the end users of the new infrastructure, cruise operators, the Commission concluded that they would not obtain an undue advantage. They would have equal and non-discriminatory access to the new infrastructure. The docking fees charged by PMPF are similar to the fees charged by other comparable ports in the EU and allow PMPF to cover its operating costs. This is an indication that “the docking fees charged by PMPF do not provide an undue advantage to the users of port of Katakolo.”


Do you know we also publish a journal on State aid?

EStAL banner
The European State Aid Law Quarterly is available online and in print, and our subscribers benefit from a reduced price for our events.


 

Compatibility of the aid

The Commission assessed the compatibility of the aid directly on Article 107(3)(c) TFEU and, as is its normal practice, it carried out a detailed economic appraisal according to the methodology of the “balancing test”.

It was not difficult for the Greek authorities to demonstrate that the project served an objective of common interest (it strengthened cohesion) and that the aid was an appropriate instrument, as the construction of the port infrastructure could not be achieved through other means.

As regards the necessity of the aid, the cost-benefit analysis had proven that the project would have a negative net present value. This showed that it would not be undertaken by a private investor. The Commission acknowledged that the aid had an incentive effect and observed that it “has consistently accepted that port infrastructure projects require considerable capital investments that can only be recovered in the very long term, and their economic viability may not normally be ensured without public funding.” [paragraph 68] (in this connection, see the Commission decisions cited above)

Although the amount of aid in this case is exceptionally large (aid intensity of 91.23%), the Commission nonetheless concluded that it was proportional. The Commission added that in the case of the port of Klaipeda, the aid intensity was 65%, while in the case of the Augusta port, the aid intensity was 69%. It went on to explain that “the aid intensities of different infrastructure projects at different ports are not directly comparable. The necessity for public funding for each project is a function of certain variables, such as the kind of activities to be carried out with the infrastructure, volumes of traffic, expected revenues, costs for constructing the infrastructure, etc., which are specific to the features of each specific infrastructure project.” [paragraph 72]

The decisive element in the assessment of the proportionality of the aid was that the “the public funding provided for this project is in line with the funding gap ratio identified for the project, namely of 91.23%. Therefore the aid is limited to what is necessary in order to make the project feasible.” [paragraph 74] In other words, the aid merely served to make the project break even. The must have thought that the PMPF did not derive an undue advantage, apart, of course, from the fact that it could carry out a project that would not be possible without state intervention.

On the basis of the above considerations and because the aid would not cause any excessive distortion to competition between ports, the Commission declared the aid to be compatible with the internal market.

The confusion between the necessity and proportionality of the aid

The reasoning of the Greek authorities and that of the Commission appears to be solid. It is not. A simple example can reveal the fault in their reasoning. Of course, I hasten to add that without having access to the raw data used in the cost-benefit calculation any criticism of this decision has to be circumspect. My purpose, however, is not to take exception with the precise numbers but to explain why these calculations alone cannot prove the proportionality of the aid.

Assume that the initial investment cost, V, of the project is 100. This cost is to be financed by 20 of own contribution by the beneficiary and 80 of state aid. The aid intensity is therefore 80%. Now, assume that the operating cost, P, over the life of the project is 20 and the financial return, r, which is factored in the cost-benefit analysis is 5%. That is, the total cost, TC, of the project is: TC = V + P + r = 125.

The expected revenue, R, over the life of the project is 25. This means that a cost-benefit analysis shows a deficit, D, of – 100. That is, R – TC = 25 – 125 = – 100 = D. The ratio of the deficit D over the total cost TC is 100/125 = 80%. This is the so-called “funding gap” which the Greek authorities identified in this case. It is the same as the rate of aid intensity. But the fact that the two ratios are the same is largely meaningless.

It is absolutely clear that a project with a deficit or financial gap of 80% would never go ahead. This proves the necessity of the aid. But it does not prove that the aid is proportional. In the example above, I started from the position that the aid is 80% of the initial investment cost. But note that the 5% return on the overall project, which appears to be very reasonable, in fact corresponds to a return of 25% [25/20 = 1.25%] to the owner/operator of the project who in this case is PMPF. To bring the return or profit for PMPF down to a level that is normal for port operators, its contribution would have to be raised to 23.80 [25/23.80 = 1.05%]. The aid will then have to be lowered to 76.20 instead of 80, with the aid intensity dropping to 76.2% instead of 80%. But the funding gap of the project as a whole is still 80%.

This example demonstrates that the overall profitability of a project is a distinctly different issue from the question of whether the contribution of the aid recipient is sufficient and whether the aid is proportional.

—————————————–

[1] The text of the Commission decision can be accessed at:

http://ec.europa.eu/competition/state_aid/cases/246700/246700_1444527_188_2.pdf

Tags

About

Phedon Nicolaides

Dr. Nicolaides was educated in the United States, the Netherlands and the United Kingdom. He has a PhD in Economics and a PhD in Law. He is professor at the University of Maastricht and the University of Nicosia. He has published extensively on European integration, competition policy and State aid. He is also on the editorial boards of several journals. Dr. Nicolaides has organised seminars and workshops in many different Member States, and has acted as consultant to several public authorities.

Related Posts

12. Nov 2024
State Aid Uncovered by Phedon Nicolaides
State Aid to Support Production of Penicillin in the EU - State Aid Uncovered photos 19

State Aid to Support Production of Penicillin in the EU

Introduction The Commission’s block exemption regulations and the guidelines do not cover exhaustively State aid for all conceivable policy objectives. For example, there are no specific rules on investment subsidies for large enterprises in non-assisted regions. This does not mean that Member States may not grant State aid to a large company to manufacture a product they consider important. Rather, […]
23. Apr 2024
State Aid Uncovered by Phedon Nicolaides
Pricing of Access to Infrastructure for the Treatment of Waste Water - State Aid Uncovered photos 10

Pricing of Access to Infrastructure for the Treatment of Waste Water

Introduction It is not unusual for EU courts to refer to the Commission’s 2016 Notice on the Notion of State Aid as a means of shedding light to the more obscure aspects of that notion. What is very unusual is for EU courts to treat the Notice as if it has the same status as the guidelines that bind the […]
09. May 2023
State Aid Uncovered by Phedon Nicolaides
Development of Affordable Housing - Untitled design 15

Development of Affordable Housing

Introduction The provision of social housing can be designated as a service of general economic interest and can be publicly funded under the Commission decision 2021/21. Member States have to show that there is a real social need and limit access to social housing to those persons who cannot afford what the market provides; i.e. low-income or vulnerable persons such […]
04. Apr 2023
State Aid Uncovered by Phedon Nicolaides
Compensation for Damage Caused by COVID-19 Combined with Rescue Aid - dddddddddd

Compensation for Damage Caused by COVID-19 Combined with Rescue Aid

Introduction Member States are allowed to grant state to compensate undertakings for damage they suffer as a result of a natural disaster or exceptional occurrence. But, it is not always easy or possible to disentangle the damage caused by such an unforeseen event from losses caused by mismanagement or changes of market conditions. The art and science of calculating the […]
25. Jan 2022
State Aid Uncovered by Phedon Nicolaides
Duplication of Infrastructure Does not Promote Regional Development - Social Media posts 6

Duplication of Infrastructure Does not Promote Regional Development

A private investor is not interested in regional development. A private investor recoups its investment in infrastructure from revenue from the operation of that infrastructure. Duplication of infrastructure does not contribute to regional development. Introduction In 2015 the European Commission caused a buzz in the State aid community when it decided that investment aid granted to a small Polish airport […]
30. Nov 2021
State Aid Uncovered by Phedon Nicolaides
Public Funding of an Undertaking in a Closed Sector - Blog Visual 48

Public Funding of an Undertaking in a Closed Sector

Public funding of undertakings in sectors closed to competition does not constitute State aid. A sector is closed to competition when competition on and for the market is precluded by law. Introduction Determining when State aid does not affected cross-border trade is both difficult and tricky. But there is one exception; when the sector is closed to competition. A sector […]
13. Apr 2021
State Aid Uncovered by Phedon Nicolaides
State Guarantee to an Energy Project - StateAidHub blogpost15 gas

State Guarantee to an Energy Project

A state guarantee can bridge the funding gap of an infrastructure project. Introduction State aid rules allow energy infrastructure projects to be supported by as much aid as is necessary to bridge their “funding gap”; i.e. the difference between the initial investment cost and the present value of their expected net operating revenue which is the future gross revenue minus […]
02. Jun 2020
State Aid Uncovered by Phedon Nicolaides
Euromünzen

i) Investor-State Arbitration ii) Recovery of Incompatible State Aid iii) State Aid Scoreboard 2019

Member States abolish bilateral investment treaties between themselves. When the Commission orders recovery of incompatible State aid, interest has to be added to the recoverable amount for the whole period of illegality regardless of any national limitation rules. In 2018, Member States granted EUR 121 billion to industry and services, EUR 6.3 billion to agriculture and EUR 50 billion to […]
26. May 2020
State Aid Uncovered by Phedon Nicolaides
State Aid for i) Water Development ii) Travel - StateAidHub blogpost21 water development travel

State Aid for i) Water Development ii) Travel

Aid to individuals in the context of social policy is compatible with the internal market as long as it is granted without discrimination on the origin of products or services. Temporary Framework: Number of approved covid-19 measures, as of 22 May 2020: 129* Legal basis: Article 107(2)(b): 9; Article 107(3)(b): 111; Article 107(3)(c): 12 * Excludes amendments to previously notified […]
03. Mar 2020
State Aid Uncovered by Phedon Nicolaides
State Aide_Infrastructure

Public Funding of Infrastructure without State Aid

The existence of State aid must be checked at the level of both the direct and indirect beneficiaries who are the owners and users of infrastructure, respectively. If payments to private land owners are to be free of State aid, they must be calculated on the basis of an objective formula that takes into account the size and value of […]