A public authority can act as a private investor in paying to avoid costly contractual clauses. A public authority can act as a private investor in paying to bring forward future revenue.

Introduction
 
When a market operator invests to make profit, its underlying logic is the same as when it pays to avoid losses. In both cases it is motivated by the desire to maximise the value of its assets. In the first case it avoids loss of potential profit while in the second case it avoids loss of actual profit. This is the reason why the hypothetical private investor who underpins the legal concept of the market economy investor always takes into account all options. Also options which lie far into the future are not ignored. With the proper discounting they can be compared to options and values which are available today.The case reviewed in this article is a classic example of how examining only some of all potentially available options can lead to wrong conclusions. The case concerns an appeal brought by the Netherlands against the Commission which had found that a Dutch municipality did not comply with the MEIP. The payments it made to a property developer were found by the Commission to constitute incompatible aid which had to be recovered.The Netherlands succeeded to have the Commission decision annulled not because it proved that the municipality was a shrewd investor but simply because it demonstrated that the Commission ignored that the municipalities had limited options to recoup its investment and that alternative courses of action could have been costlier.
 
Background
 
Case T-186/13, Netherlands and others v Commission[1] was an application for annulment of Commission decision 2013/247 [OJ L 148, 1/6/2013].In 2004, the municipality of Leidschendam-Voorburg established a 50/50 public private partnership with construction company SJB. The purpose of the PPP was to develop an area in the centre of the municipality. The land and (run-down) buildings belonged to the municipality. SJB agreed to pay a fee to the municipality, via the PPP. The fee corresponded to the then value of the land plus certain other payments.

Do you know we also publish a journal on State aid?

EStAL banner
The European State Aid Law Quarterly is available online and in print, and our subscribers benefit from a reduced price for our events.


 

It is customary in the Netherlands for developers to pay land owners [in this case the municipality] when they start construction. Moreover, it is standard practice for developers not to start construction until a certain number of housing units are pre-sold. The original 2004 agreement contained a clause that SJB would start construction if 70% of the units were pre-sold. SJB intended to partly finance the project by pre-selling housing units. Because of delays in obtaining building permits and a slow-down in the housing market, SJB did not pre-sell enough units and, as a result, construction did not start. In 2010, the PPP decided to change the initial terms of the agreement and allow SJB to pay a smaller amount to the municipality. The Commission found that the change in the agreement and the lower amount constituted incompatible State aid. Under the 2004 agreement, the municipality appeared not to be liable for any market risk. Therefore, the Commission concluded that the municipality had no reason to accept a lower payment. The amount of aid that had to be recovered was estimated at EUR 6.9 million. The table below is from the Commission decision and shows how the Commission arrived at the amount of EUR 6.9 million.
The municipality claimed that it had acted as a private investor and that SJB bore an equal reduction in revenue. In other words, the issue at hand was whether the 2010 agreement was MEIP conform.

Transfer of state resources

The General Court examined, first, whether the agreement of 2010 resulted in a transfer of state resources. The Commission claimed in its decision that since the municipality owned 50% of the PPP, no decision of the PPP could have been taken without its consent.

The Court first recalled three fundamental issues concerning transfer of state resources which were elaborated in the judgment of the Court of Justice in case C-399/10 P, Bouygues Telecom v Commission. First, there must be a reduction in the state budget or an increase in the liabilities or risks that burden that budget. Second, there must be a close link between the impact [i.e. the reduction of assets or increase in liabilities] on the state budget and the advantage that is conferred to an undertaking. Third, it is not necessary that the impact on the state budget is equivalent to the advantage that is conferred [paragraphs 70-71]. [It should be added that a fourth element that was included in the judgment of the Court of Justice in Bouygues v Commission was that several seemingly distinct measures can be subsumed to a single measure if they serve the same purpose and are chronologically close to each other.]

On the basis of the above principles and because the decision of the PPP could be attributed to the municipality, the General Court agreed with the Commission that the agreement of 2010 resulted in a transfer of state resources.

Existence of advantage and MEIP

After some preliminary observations, the General Court explained that in the case of sale of public land, the amount of aid is the difference between the market price of the land and the price at which it is actually sold. [Paragraph 77]

Then the Court found that the Commission made a serious mistake. It took the value of land in 2004 to be EUR 7.2 million on the basis of a valuation by an independent expert. However, in the Court’s view, the Dutch authorities did not accept that valuation as corresponding to the market price of the land [paragraph 81]. The Commission responded by pointing out that the exact market price was not relevant. What was relevant was the agreed price in the 2004 agreement. No private investor would accept a lower price six years later when it had secured a higher price through a contract [paragraph 83]. For this reason the Court had to examine whether a private investor in similar circumstances would have accepted such a change in the contract.

The General Court faulted again the Commission for not taking into account all the relevant facts at the time the 2010 agreement was signed. The Commission appeared to have ignored that SJB refused to proceed to the construction phase because it had invoked a number of escape clauses in the 2004 agreement concerning in particular delays in building permits. The Commission also appeared to neglect that the municipality had limited options because the building site was of little interest to other developers. [Paragraphs 98-108]

With respect to the latter point, the Commission counter-argued that a private investor would not be concerned about leaving a deserted area in the centre of town. If the municipality cared about the condition of its town centre it would act instead as a public authority. [Paragraph 109]

Although the General Court did not reject the argument concerning the interference of potential public policy objectives, it noted that the Commission did not try to examine whether the municipality would have an interest akin to that of a private investor in ensuring the speedy completion of the project so that it would expedite receipt of payment [paragraph 114]. In addition, the municipality would want to start receiving income as soon as possible from fees it could charge to owners of both commercial and residential space [paragraph 125].

For all of the above reasons, the General Court annulled the contested Commission decision.

Conclusion

It is worth summarising the reasoning of the General Court in faulting the Commission. The Court did not find that the municipality had acted like a private investor. It only concluded that the Commission failed to take into account all the relevant factors which could have influenced the decision of a private investor. These factors were:

i) the contractual escape clauses that were invoked by SJB,
ii) the limited options of the municipality to re-tender the project or find alternative uses for the land and
iii) the desire of the municipality to expedite the potential payments it could receive from completion of the project.

In other words, contractual constraints are a cost that an investor could legitimately pay to avoid. Bringing forward income streams is a benefit that an investor could legitimately pay to realise.

The Market Economy Investor Principle Applies also to Avoidance of Losses - Banner EssentialsBerlin Hub

—————————————————————–

[1] The full text of the judgment can be accessed at:

http://curia.europa.eu/juris/liste.jsf?language=en&num=T-186/13.

 

 

Tags

Über

Phedon Nicolaides

Dr. Nicolaides was educated in the United States, the Netherlands and the United Kingdom. He has a PhD in Economics and a PhD in Law. He is professor at the University of Maastricht and the University of Nicosia. He has published extensively on European integration, competition policy and State aid. He is also on the editorial boards of several journals. Dr. Nicolaides has organised seminars and workshops in many different Member States, and has acted as consultant to several public authorities.

Kommentar

  1. von José Antonio Rodríguez-Miguez

    Another interesting comment focused on an essential topic on state aid practice. The MEIP or, as Commission uses to say now, the “market economy operator (MEO) test” [See the Draft Commission Notice on the notion of State aid pursuant to Article 107(1) TFEU at http://ec.europa.eu/competition/consultations/2014_state_aid_notion/draft_guidance_en.pdf p. 21et seqs. ] it always a “risk” task for the Commission, as recent jurisprudence proofs. But, as Prof. NICOLAIDES points out again in this new interesting post, it’s basically a proof question, in which the Commission has the harder work. Thanks for this new post.

Hinterlasse eine Antwort

Zusammenhängende Posts

02. Jul 2024
State Aid Uncovered von Phedon Nicolaides
Green Energy Certificates - State Aid Uncovered photos 3

Green Energy Certificates

Introduction Certificates that confirm that an undertaking has bought a certain amount of electricity from renewable sources do not normally involve State aid because they are not traded. However, when they are tradeable and are granted by a public authority for free or for a fee that falls below their market value, they normally involve State aid as they confer […]
18. Jun 2024
State Aid Uncovered von Phedon Nicolaides
Obligations Imposed by the State Cannot Justify Tax Exemptions - State Aid Uncovered photos 18

Obligations Imposed by the State Cannot Justify Tax Exemptions

Introduction Over the past decade or so, the European Commission has found that multiple port operators have benefitted from State aid in the form of tax exemptions. This aid was in all cases found to be incompatible with the internal market, despite the claims of the port operators that the state had imposed on the public service obligations or that […]
04. Jun 2024
State Aid Uncovered von Phedon Nicolaides
Special Tax Treatment for a Major Infrastructure Project - State Aid Uncovered photos 16

Special Tax Treatment for a Major Infrastructure Project

Introduction In April 2013, the Commission received a complaint alleging that State aid had been granted to the Oresund fixed link. The link is a major transport infrastructure project consisting of a bridge, an artificial island and tunnels between Denmark and Sweden. In October 2014, the Commission concluded that the public funding of the hinterland road and rail connections was […]
07. Mai 2024
State Aid Uncovered von Phedon Nicolaides
Public Procurement and State Aid - State Aid Uncovered photos 2

Public Procurement and State Aid

Introduction A faulty public procurement procedure or the use of discriminatory selection criteria can confer an advantage on the chosen undertaking that may constitute an advantage in the meaning of Article 107(1) TFEU. The result will be infringement of both public procurement rules and State aid rules. A recent Commission decision, SA.47650, is instructive on how Member States should design […]
23. Apr 2024
State Aid Uncovered von Phedon Nicolaides
Pricing of Access to Infrastructure for the Treatment of Waste Water - State Aid Uncovered photos 10

Pricing of Access to Infrastructure for the Treatment of Waste Water

Introduction It is not unusual for EU courts to refer to the Commission’s 2016 Notice on the Notion of State Aid as a means of shedding light to the more obscure aspects of that notion. What is very unusual is for EU courts to treat the Notice as if it has the same status as the guidelines that bind the […]
09. Apr 2024
State Aid Uncovered von Phedon Nicolaides
An Innovative Risk-Sharing Tool for the Support of an LNG Terminal - State Aid Uncovered photos 8

An Innovative Risk-Sharing Tool for the Support of an LNG Terminal

Introduction The Commission, in decision SA.102163, authorised State aid for the construction of a terminal for liquefied natural gas [LNG] in Brunsbüttel, Germany.1 The project consists of an LNG import, storage and distribution facility with annual capacity of about 10 billion m3. The project is carried out by the German LNG Terminal GmbH [GLNG] which has three shareholders: the Dutch […]
02. Apr 2024
State Aid Uncovered von Phedon Nicolaides
The Court of Justice Conflates Objective Justification with Policy Objective, in the context of Public Support of Green Electricity - State Aid Uncovered SM posts

The Court of Justice Conflates Objective Justification with Policy Objective, in the context of Public Support of Green Electricity

Introduction Suppose a Member State subsidises the installation of solar panels on the roof of a corporate building situated at number 5 on Main Street. Is this a general measure because there is no other building in the whole country with the same address? Of course, it is not a general measure. The uniqueness of the address is irrelevant. Apart […]
05. Mrz 2024
State Aid Uncovered von Phedon Nicolaides
State Aid and Arbitration of Disputes - State Aid Uncovered photos

State Aid and Arbitration of Disputes

Introduction On 22 February 2024, the Court of Justice [CJEU] delivered its judgment in joined Cases C-701/21 P and C-739/21 P, Mytilinaios v DEI & European Commission. Mytilinaios, a Greek company, and the Commission appealed against the judgment of the General Court in case T-639/14 RENV, DEI v Commission, concerning arbitration of a dispute between Mytilinaios and DEI, the main […]
20. Feb 2024
State Aid Uncovered von Phedon Nicolaides
Another Case of Indirect State Aid - State Aid Uncovered photos 4

Another Case of Indirect State Aid

Introduction On 19 May 2021, the General Court, in case T-643/20, Ryanair v Commission, annulled Commission decision SA.57116 by which it authorised State aid in favour of KLM in the context of the measures implemented by the Dutch government to address the covid-19 pandemic. In July 2021, the Commission re-adopted its original decision without the errors that had been identified […]
13. Feb 2024
State Aid Uncovered von Phedon Nicolaides
State Resources, Control and Imputability - State Aid Uncovered photos 1

State Resources, Control and Imputability

Introduction A public measure can be classified as State aid only when it is funded from state resources. Measures funded from the budgets of public authorities are always considered to be supported by state resources. However, measures not funded from state budgets may still be supported by state resources. This is because, rather counterintuitively, the concept of state resources covers […]