PART I: Combining Infrastructure Aid with SGEI Aid

PART I: Combining Infrastructure Aid with SGEI Aid - m 24 1

A provider of services of general economic interest may receive both investment aid and compensation for the extra costs of public service obligations.

 

Introduction

Governments normally support large infrastructural projects through guarantees. This is because such projects have a long life, the initial investment costs are very high and the recoupment of investment takes place over a long period through fees charged to users. Many things can happen in a period that can span several decades. Although banks and other creditors are happy to lend millions in the knowledge that there will be a steady stream of income from user fees, they also need the assurance of a state guarantee.

Energy terminals are no exception. If they have to be subsidised, normally they get a state guarantee and, if that is not enough, they receive an up-front amount to cover part of the investment costs. It is rare that they get other types of aid.

However, when Lithuania proposed to build a terminal to import liquefied natural gas [LNG] to reduce its absolute dependency on Russian gas supplied by Gazprom, it provided to the operator of the terminal both a guarantee to cover loans from the EIB and other creditors and operating aid. The operating aid was funded by a levy on the users of the terminal and final gas consumers.

The Commission, in decision SA.36740, found that both the guarantee and the revenue from the levy constituted State aid.[1] It approved both for being compatible with the internal market on the grounds that the guarantee was necessary to bridge a funding gap while the operating aid was necessary to cover the extra costs of public service obligations imposed on the terminal operator. Lithuania designated the operation of the terminal as a service of general economic interest [SGEI]. Although the decision is from November 2013, it was made public only on 4 May 2016.

The terminal was built at the port of Klaipeda and the designated builder/operator was AB Klaipedos Nafta. The operator is a majority state-owned company [72%] that was appointed without any competitive selection.

The aid granted to AB Klaipedos Nafta was partly based on Article 107(3)(c) and partly on Article 106(2) [SGEI]. This is very unusual. Therefore, this article is in two parts. Part I examines the investment aid that was granted on the basis of Article 107(3)(c) and next week Part II analyses the operating aid that compensated for the extra costs of public services obligations and was granted on the basis of Article 106(2).

Part I

The state guarantee

Lithuania granted a guarantee to cover 100% of the loans that the operator obtained from EIB and other sources. The guarantee premium was 0.1% of the total value of the loans and was backed by a 100% collateral that was secured against the property of the terminal. The duration of the guarantee matched the duration of the loans which was 20 years.

The problem here was that a 100% guarantee was not in conformity with the conditions for the valuation of guarantees laid down in the 2008 Commission notice. The Commission skipped over this issue without any explicit mention. Rather in paragraph 102 it explained the four methods it used in its decisional practice to determine the market price of a guarantee. These methods are as follows:

  1. Comparator method: The premium charged on the state guarantee is compared to the price charged by commercial creditor for a guarantee of the same amount and same risk to the same undertaking.
  2. Benchmarking method: The premium charged on the state guarantee is compared to prices of similar guarantees or instruments such as credit default swaps on the market.
  3. Costing method: The premium is worked out on the basis of the probability of default, the required return on capital and the administration costs involved.
  4. Rate differential method: This is the typical method used for guarantees that cover 100% of the loan. Since it is unlikely that a commercial creditor would offer a 100% guarantee, it is difficult or impossible to establish a market rate. Hence, in such cases the Commission calculates the amount of aid involved in a state guarantee as the difference between the interest that it would pay on the loan without the guarantee and the interest it actually pays with the guarantee minus any premium it pays for the guarantee.

Do you know we also publish a journal on State aid?

EStAL banner
The European State Aid Law Quarterly is available online and in print, and our subscribers benefit from a reduced price for our events.


 

The Commission chose the fourth approach and accepted that the difference in the financing costs of the loan could be calculated according to the following formula proposed by Lithuania:

Borrowing rate = Pre-tax required return on capital of lender + opportunity cost of funds + risk cost + administrative cost.

The risk cost was calculated according to the credit rating of Lithuania [BBB] and the quality of the collateral pledged by the terminal operator. The quality of the collateral was deemed to be high because the loss given default was only 14%.

The amount that was derived was business secret as many other amounts and rates.

The levy

The Commission first had to determine whether the revenue from the levy constituted state resources. Although it was paid by terminal users and gas consumers, it was imposed and defined by legislation, collected and used according to the terms defined in that legislation and supervised by the national energy regulator. The Commission concluded in paragraphs 91-96, that the state exercised control over it, regardless of the fact that it was not managed by a public authority.

It is amply clear now that if a public authority imposes a tax and designates a private entity to manage the proceeds according to its instructions, the proceeds will be considered to constitute State aid for the recipient of the money. Interestingly, the Commission referred to the landmark cases of Pearle [C-345/02] and Doux Elevage [C-677/11] and explained that the levy was not applied as a result of a free decision of the designated body, nor did it finance activities chosen by that body to advance its interests, as in Pearle and Doux Elevage. Rather the levy aimed to support public policy objectives.

The revenue from the levy was intended to support the financing costs of the investment as well as the fixed costs of the operation of the terminal. The amount of the levy was calculated in such a way so as to enable the operator to cover its costs and earn a reasonable return on its capital which was defined by the Lithuanian energy regulator as the regulated asset base of the terminal. The regulated asset base decreases each year in proportion to the depreciation of the assets concerned.

The formula for the levy is as follows:

Levy = (fixed costs + return on capital + administration expenses)/gas quantity

The fixed costs are given by such items as maintenance, repairs, staff costs, etc.

The return on capital is calculated on the basis of the weighted average cost of capital [WACC] before tax. It was estimated to be 7.09%.

WACC = (Rd x D) + (Re x E x 1/(1-t)), where

Rd = interest on debt

D = part of capital assumed to be financed by debt [70%]

Re = required rate of return on equity

E = part of capital assumed to be financed by equity [30%]

t = the Lithuanian corporate tax rate which stands at 15%.

The required rate of return on equity, Re, was calculated according to a variant of the formula of the capital asset pricing model:

Re = Rf + MRP x (β + (1 + (1-t) x D/E)), where

Rf = risk-free return given by a 10-year government bond

MRP = the market risk premium + a specific country premium for Lithuania

β = the beat coefficient for the specific risk of gas companies.

On the basis of the above calculations, the Commission derived the amount of the money that would be provided to the terminal operator.

Compatibility

Once the Commission established that the guarantee and the levy constituted State aid, it proceeded to assess their compatibility with the internal market.

The investment aid was assessed according to the criteria in the balancing test which are largely reflected in the current common compatibility principles. The Commission concluded that:

  • The aid was in the common interest because the project contributed to energy security by reducing the dependency of Lithuania on Gazprom. Security of energy supply has been recognised by the Court of Justice as being an “overriding reason in the public interest” [see C-105/12, Essent].
  • The aid was an appropriate instrument because the reduction in dependency on Gazprom could not be regulated.
  • The aid was necessary because, despite the very high of gas in Lithuania, the market was not making the necessary investments to expand supply [this could have been caused by the Gazprom’s links to a number of gas providers in Lithuania]. Funding gap analysis showed that the terminal would not be viable without the aid. Interestingly, Lithuania also submitted information to demonstrate that investment in other projects would not reduce its dependency. For example, construction of pipelines to Latvia would not be effective because Latvia was equally dependent on Gazprom, while a pipeline to Poland would not be operational before 2020.
  • The aid had an incentive effect because the net present value without aid was negative and the internal rate of return was below the WACC. In addition, the Commission verified that the terminal operator was not legally obliged to construct and operate the terminal under EU regulations on energy.
  • The aid was proportional because it did not result in any excess profits for the operator as the IRR with aid was still lower than the WACC.
  • The aid was not expected to cause any undue distortion of competition as it would increase competition on the gas market. Also the terminal operator would pay the same fee as other users of the port facilities and the terminal itself would be open to all users on a non-discriminatory basis.

On the basis of the above assessment, the Commission concluded that the aid linked to investment was compatible with the internal market on the basis of Article 107(3)(c).

However, it could not authorise operating aid [revenue from the levy on users and consumers] on the basis of Article 107(3)(c). Therefore, it considered the applicability of Article 106(2) on SGEI and in particular, whether, the funding arrangements complied with the conditions in the 2012 SGEI Framework.

—————————————————-

[1] The full text of the decision can be accessed at:

http://ec.europa.eu/competition/state_aid/cases/250416/250416_1542635_190_2.pdf.

Tags

Über

Phedon Nicolaides

Dr. Nicolaides was educated in the United States, the Netherlands and the United Kingdom. He has a PhD in Economics and a PhD in Law. He is professor at the University of Maastricht and the University of Nicosia. He has published extensively on European integration, competition policy and State aid. He is also on the editorial boards of several journals. Dr. Nicolaides has organised seminars and workshops in many different Member States, and has acted as consultant to several public authorities.

Hinterlasse eine Antwort

Zusammenhängende Posts

26. Sep 2023
State Aid Uncovered von Phedon Nicolaides
Non-imposition of Fines on Non-illegal Behaviour - Untitled design 9

Non-imposition of Fines on Non-illegal Behaviour

Introduction Advantage is any benefit that an undertaking obtains from the intervention of the state. In some situations, however, an undertaking may derive an advantage the non-intervention of the state or, more broadly, from the failure of the state to act. This would be the case where the state does not charge a fee to a user of a state […]
13. Apr 2021
State Aid Uncovered von Phedon Nicolaides
State Guarantee to an Energy Project - StateAidHub blogpost15 gas

State Guarantee to an Energy Project

A state guarantee can bridge the funding gap of an infrastructure project. Introduction State aid rules allow energy infrastructure projects to be supported by as much aid as is necessary to bridge their “funding gap”; i.e. the difference between the initial investment cost and the present value of their expected net operating revenue which is the future gross revenue minus […]
03. Nov 2020
State Aid Uncovered von Phedon Nicolaides
Evaluation of EU State Aid Rules: Need for Greater Transparency - office 4249408 1920

Evaluation of EU State Aid Rules: Need for Greater Transparency

On Friday, 30 November 2020, the European Commission published a Staff Working Document [SWD(2020) 257 final] presenting and assessing the results of the evaluation of the main State aid rules of the EU. The SWD explains the aims of the State Aid Modernisation [SAM] that was launched in 2012 and summarises the findings of the Fitness Check of the GBER, […]
11. Jun 2020
Guest State Aid Blog von Erika Szyszczak
When State Aid Gets Political - brexit 3870554 1920

When State Aid Gets Political

We are happy to receive a guest comment on the EU – UK post-Brexit trade negotiations from Professor Emerita, Erika Szyszczak, who is a Fellow of UKTPO at the University of Sussex. This is a longer version of an earlier Blog published on the UKTPO website. Control over State aid is a stumbling block for the future of an EU […]
09. Jun 2020
State Aid Uncovered von Phedon Nicolaides
pills on money

Private Investor and Preferential Regulatory Treatment

The existence of an advantage has to be proven, not presumed just because its absence cannot be confirmed. Preferential treatment may distort competition but it is not necessarily State aid if there is no transfer of state resources. Temporary Framework: Number of approved covid-19 measures, as of 5 June 2020: 148* Legal basis: Article 107(2)(b): 13; Article 107(3)(b): 125; Article […]
05. Mai 2020
State Aid Uncovered von Phedon Nicolaides
corona virus poster

Non-recovery of Incompatible State aid Is Costly

Legal and practical difficulties in the recovery of incompatible State aid do not constitute justifiable “absolute impossibility”. Temporary Framework On 1 May, the total number of State aid measures to combat covid-19 approved by the European Commission reached 102. Their legal basis was: Article 107(2)(b): 9; Article 107(3)(b): 86; Article 107(3)(c): 7   Introduction The 2020 Temporary Framework for State […]
27. Apr 2020
State Aid Uncovered von Phedon Nicolaides
corona virus poster

Identification of Undertakings in Difficulty

A company is in difficulty if, in practice, its accumulated net losses exceed 50% of its subscribed capital, regardless of whether the subscribed capital is formally written down. The classification of a company as being in difficulty is independent of the sector in which it operates and of whether a private investor would be willing to invest in it. Temporary […]
17. Apr 2020
Guest State Aid Blog von Michail Kamperis
Corona Virus

COVID-19 Measures Adopted and State Aid Measures (Hopefully) to Be Adopted: An Update from Cyprus

We are happy to share with you an update on the Covid-19 measures that are or will be adopted in Cyprus. Our guest auhor Michail Kamperis is a lawyer and partner at the law firm of Ierotheou, Kamperis & Co. LLC Nicosia, Cyprus. * Sign up for our free news alert  Sign Up For Free   Cyprus is one of […]
09. Apr 2020
Guest State Aid Blog von Lexxion Publisher
Woman sitting by the computer

Follow Up Webinar with Phedon Nicolaides on ‚COVID-19 and State Aid Law‘ on 20 April

The European Commission is working on quickly adapting the existing State aid legal framework to address the current Covid-19 pandemic. Join us on 20th April from the comfort and safety of your (home) office to get an insider update on the Covid-19 response by State aid experts from the European Commission and national governments. ✓ Join from wherever you are – […]
23. Dez 2019
State Aid Uncovered von Phedon Nicolaides
A Preferential Electricity Tariff Is Selective, Confers an Advantage and Distorts Competition - StateAidUncovered blogpost53 Alouminion

A Preferential Electricity Tariff Is Selective, Confers an Advantage and Distorts Competition

A judicial decision on interim measures is a selective measure. The private investor test does not apply to judicial decisions on interim measures. Introduction On 11 December 2019, in case C‑332/18 P, Mytilinaios Anonymos Etairia — Omilos Epicheiriseon v European Commission, the Court of Justice probably wrote the last chapter in a long-running case concerning privileges that had been granted […]