Regional Investment Aid and Sale of Land

Regional Investment Aid and Sale of Land - m 19

A company that applies for State aid is considered to acquire a right to that aid when assurances it has received from the granting authority can be enforced in court. The price of land can be reduced by the cost that a new owner would expend to make the land usable.

 

Introduction

In decision SA.40448, the Commission assessed aid that was granted by Germany to Getzner Textil Weberei [GTW].[1] The Commission’s assessment followed an investigation which had been prompted by a complaint.

The German beneficiary of the aid is owned by an Austrian company. GTW is based in Germany and employs about 75 persons who manufacture textiles. GTW transfers all of its production to its Austrian parent company, which then sells it in West Africa.

GTW was alleged to have received a grant of €12.6 million to support investment in the construction of a new production facility and in the acquisition of 108 weaving machines totalling €47 million. In addition, it was claimed that GTW bought public land at a price below market level.

Compatibility of the aid

The Commission examined both the investment grant and the sale of land. With respect to the grant, there was no doubt that it fell within the scope of Article 107(1) TFEU. The only contentious issue at hand was its compatibility with the internal market.

The grant was provided in March 2014. Although, the period of validity of the then regional block exemption regulation [Regulation 1628/2006] ended on 31 December 2013, it was extended to 30 June 2014 when the new General Block Exemption Regulation [Regulation 651/2014] came into force. Hence the Commission considered that the legal basis for the grant was Regulation 1628/2006.

 

It then proceeded to determine whether the aid was granted in compliance with the provisions of that regulation. As most of the provisions for regional aid have changed since then, the findings of the Commission are not reviewed here, with the exception of the following interesting points.

With respect to the incentive effect, the Commission observed that the requirements of the Regulation were satisfied “(28)(6) as, prior to the start of works, the beneficiary had applied for aid and the responsible authority had confirmed in writing that, subject to the final outcome of a detailed verification, the project met the conditions of eligibility laid down by the scheme. Specifically, the application took place on 11 March 2014 and works on the investment started on 1 April 2014. The granting body, the Thüringer Aufbaubank, confirmed in writing on 13 March 2014 that, subject to a detailed examination of the fulfilment of all applicable conditions, the investment project is eligible for regional investment aid. The Commission would like to add that the granting did not take place via a document in which the aid measure was promised on 24 January 2014 because the document clearly states it is a “draft” (Entwurf), and it contains an indication that an application will need to be submitted by 15 April. Thus, this document could not create an irrevocable entitlement (verbindliche Zusicherung) to the aid measure which would be enforceable in court by the beneficiary. Thus, the incentive effect requirements were properly complied with.”

This assessment is still relevant under the current rules. The only credible indication that a public authority is committed to fund a project is a document that confers to a company a legal right to State aid. The Commission clarified in this case that the proof that such a right had been granted was that it could be enforced by a court.

With respect to the overall size of the investment and whether the total amount exceeded the individual notification threshold, the Commission noted that “(28)(9) the allegedly planned investments by the beneficiary’s parent company in Austria do not need to be added to the €47 000 000 investment costs. This is because pursuant to Point 60 of the RAG, the assessment of whether or not different investment projects constitute a “single investment project”, will be determined on the basis of technical, functional and strategic links and the “immediate geographical proximity” (emphasis added). Given that the alleged investment is taking place in Austria, this immediate geographical proximity is not present.”

Again, the same principle would be relevant today, even though the rules on single projects have changed and they refer to projects within NUTS 3 regions. Certainly investments in other Member States must be ignored because no NUTS 3 region extends from one country to another.

With respect to aid granted by another Member State to the parent company, the Commission rejected the claims of the complainant. “(28)(12) Finally, any export aid allegedly granted to the beneficiary’s parent company in Austria cannot be cumulated with the regional investment aid measure, as, assuming it has been granted, it would have been granted for different eligible costs and for a different purpose/project, and thus it would not fall under the situations of cumulation that Article 6 of the Regional Block Exemption Regulation prohibits. In fact, the aid would even be granted by different Member States.”


Do you know we also publish a journal on State aid?

EStAL banner

The European State Aid Law Quarterly is available online and in print, and our subscribers benefit from a reduced price for our events.


 

The sale of land

In order to determine whether the land was sold below market value, “(31) the Commission carried out an evaluation of the credibility of the independent assessor’s evaluation of the land prepared in 2015, with a view towards establishing whether the price paid by the beneficiary reflected the market value at the time of the sale in the spring of 2014.”

“(32) As regards, the methodology of assessing the value of the land in question, the Commission would like to point out that the Complainant did not offer any discernible methodology for the calculation of the land’s value. It merely questioned the validity of the €17.64/m2 value (determined in 2007) and referred to square meter values that were allegedly market values in 2014 at the time of sale to Getzner Textil Weberei GmbH according to the Bundesland Thueringen and the Thueringer Aufbaubank. It did not submit any proof that can be convincing that the square meter value of the land in question could indeed have been as high as €40 or even €60 at the time of its sale to Getzner Textil Weberei GmbH. The allegation relating to the square meter value was supposed to be proven through a print out of the “Bodenrichtwertkarte” which allegedly showed that the value was €40/m2 on 31 December 2012. However, the only element in the attached print out possibly showing a €40/m2 value could be the figure “40” in the middle of a plot of land that is allegedly next to the piece of land in question. It cannot be inferred from any other element in the attached print out that the square meter value would have indeed been €40 on 31 December 2012, as it could have designated an area larger than one square meter. The value, even if it is assumed that it refers to a square meter price, refers to a different plot and in a different year. Moreover, there is no explanation whatsoever in that print out on how a square meter value of €40 could have been determined. Further, the Complainant did not offer any further explanation or proof why the square meter value of the land in question would have been €60 in the spring of 2014 according to the Bundesland Thueringen and the Thüringer Aufbaubank.”

 

The Commission went on to remark that “(33) on the other hand, the independent expert evaluator’s assessment appears to be based on a credible methodology which is contained in an officially signed land value evaluation report. It based the basic square meter price on the official reference value database (the “Bodenrichtwertkarte”) applicable to the location, which was indicated as €15/m2 on the relevant date for use without any construction on it. The reference value of €15/m2 resulted in a theoretical value of €356 940. From this, 20% (€71 388) was deduced given that an “unevenness” or relatively steep decline in the ground required corrective action. The final value was thus determined as €276 000.” “(34) The Commission finds this evaluation methodology credible. The Commission also sees no reason to doubt either the independence of the expert evaluator or his expertise given his professional qualifications described in recital 18(4).”

To be fair, if the Commission adopted the same rigorous approach towards its own assessment, it should have questioned how the expert had arrived at the 20% deduction. Was it based on calculation of the actual cost of levelling the land? More importantly, however, the price of land is rarely equal to the value derived by the buyer. Normally, the price reflects the value of the land to an alternative buyer. Hence, it is not obvious why that plot needed corrective action before it could be used by an alternative buyer. The expert should have provided explanation for the claimed need.

This explanation should have been required by the Commission, given that in the very next paragraph in the decision, the Commission found “(35) convincing the German authorities’ description of the efforts by the city of Gera to sell the property, which was almost successful vis-à-vis a third party in 2011 at a price highly comparable to the price paid by the beneficiary. The Commission would also like to point out that it does not see any reason to doubt the veracity of the information relating to the actual sales prices at which comparable real estate property sales took place (i.e. between €9.5 and €12/m2 between 2010 and 2014). The €12/m2 price paid by Getzner Textil Weberei GmbH in 2014 is also in line with these prices. It is also credible to the Commission that the value of the property had to be adjusted given an unevenness of the ground, which resulted in a decrease of the value of the property. Finally, the Commission would like to point out that indeed even the German authorities referred to information from the Thuringian State and the Thüringer Aufbaubank that property prices in Thuringia varied between €5.34 and €60/m2 in the time period in question. This, however, is not inconsistent with the real estate property assessor’s opinion that the value of the land in question was €276 000 (and originally based on a €15/m2 price) which is in the band of values indicated by the Thuringian State and the Thüringen Aufbaubank.”

Conclusion

On the basis of the above analysis, the Commission found that the grant was compatible with the regional block exemption regulation, while the sale of land was free of State aid.

The finding of compatibility does not appear to be problematic. But the conclusion that the land sale did not contain State aid is a bit more controversial. The Commission appeared to consider more reasonable the valuation assumptions of the independent expert.

At any rate, this case demonstrates that every assumption in valuation of assets has to be supported by reasonable explanations and credible evidence.

——————————————————-

[1] The full text of the decision can be accessed at:

http://ec.europa.eu/competition/state_aid/cases/264573/264573_1841842_58_2.pdf.

Tags

Über

Phedon Nicolaides

Dr. Nicolaides was educated in the United States, the Netherlands and the United Kingdom. He has a PhD in Economics and a PhD in Law. He is professor at the University of Maastricht and the University of Nicosia. He has published extensively on European integration, competition policy and State aid. He is also on the editorial boards of several journals. Dr. Nicolaides has organised seminars and workshops in many different Member States, and has acted as consultant to several public authorities.

Hinterlasse eine Antwort

Zusammenhängende Posts

20. Aug 2024
State Aid Uncovered von Phedon Nicolaides
Incentive Effect of State Aid to a Large Investment Project - State Aid Uncovered photos 7

Incentive Effect of State Aid to a Large Investment Project

Introduction The Commission pays particular attention to the incentive effect of aid to large projects that are undertaken by international companies which, by definition, are mobile and can choose from many different locations where to establish their operations. Not only must the aid recipient prove, on the basis of credible evidence, that without the aid the investment would not be […]
12. Sep 2017
State Aid Uncovered von Phedon Nicolaides
Concession Agreements Free of State Aid - concessions State aid airports

Concession Agreements Free of State Aid

Awards of concession contracts should follow a procedure which is open, transparent, non-discriminatory and unconditional. Prices may be regulated to prevent excessive prices and profits. But, the concession fee may be adjusted to enable the concessionaire to earn a sufficient return.   Introduction This article examines the link between State aid and concession agreements. In decision SA.44259, the Commission considered […]